The experts of 8.2 have examined more than 15,000 single turbines in 15 years: commissioning assessment, end of warranty assessment, recurring assessments, damage analysis, blade inspections, video endoscopy, vibration analysis etc. No other consultant worldwide has assessed this amount of turbines. The reference list does not take into account single turbines and small wind parks assessments.
Onshore
| Project | Services | Remarks | Year |
|---|---|---|---|
|
Germany/France bond portfolio, 44 wind farms |
Technical Due Diligence, negotiation assistance |
350 MW | 2006 -20077 |
|
Germany bond portfolio, 16 wind farms |
Technical Due Diligence | 200 MW | 2006–2007 |
|
Germany 1 wind farm |
Technical assessment | 40 MW | 2006 |
| Germany / Italy / Netherlands, several projects |
Project advisory, cost analysis, Due Diligence, technical assessments |
– | 2007 |
| Several wind parks in Germany | Technical assessments | 80 MW | 2006–2008 |
| Germany/France, bond portfolio, 44 wind farms |
Portfolio supervision | 350 MW |
2007–2027 |
| Germany, several wind farms |
Technical assessment |
84 MW (Gamesa turbines) |
2007 |
| Marocco, 1 wind farm |
Technical assessment prior to sale of wind farm |
50 MW |
2007 |
| Norway, 1 wind farm |
End of warranty inspection |
40 MW |
2007 |
| Spain, 1 wind farm |
Endoscopy of 90 turbines |
100 MW |
2007 |
| Power Wind |
Turbine Due Diligence of a new turbine |
– | 2007–2008 |
| Fuhrländer |
Turbine Due Diligence of a new turbine | – | 2007 |
| Vensys |
Turbine Due Diligence, general technology advisory, especially blades | – | 2007–2008 |
| Germany, bond portfolio, several wind farms |
Technical Due Diligence |
180 MW |
2008 |
| MTorres, Fuhrländer, Vensys |
Due Diligence of turbines, negotiation assisstance |
- |
2008 |
| Marocco, 1 wind farm |
Full engineering services, farm layout, electrical layout etc. |
300 MW |
2008 - 2009 |
| USA, 2 wind farms |
End of warranty assessments, commissioning assessments, fire hazard check, compliance with standards |
– | 2008 |
| France, 1 wind farm |
Commissioning assessment |
70 MW |
2008–2009 |
| Germany, 1 wind farm |
Technical Due Diligence including financial modelling |
170 MW |
2009 |
| Germany, portfolio, 6 wind farms |
Technical Due Diligence |
- |
2009 |
| Germany, 1 wind farm |
Technical Due Diligence |
23 MW |
2009 |
| Germany, 1 wind farm |
Technical Due Diligence |
55 MW |
2009 - 2010 |
| Italy, 1 wind farm |
Technical inspection, damage root cause analysis, construction and repair monitoring, blade inspection |
124 MW |
2009 |
| Turkey, portfolio, several wind farms |
Technical Due Diligence |
270 MW |
2009 |
| Bulgaria, 2 wind farms |
Technical Due Diligence |
40 MW |
2009 |
| Costa Rica, 1 wind farm |
Commissioning assessment |
49.5 MW | 2009 |
| Egypt, 1 wind farm |
Damage analysis |
- | 2009 |
| Azerbaijan, 1 wind farm |
Commissioning assessment |
2 MW (2xV52) |
2009 |
| Croatia, several wind farms |
Planning assisstance |
142 MW |
2009 - 2010 |
| Due Diligence of turbine prototypes |
Inspection, document review, video/borescopic reports, blade inspections |
– |
2009 |
| Turbine and company Due Diligence |
Due Diligence of the manufacturer Clipper and DeWind |
- |
2009 |
| Vestas |
Turbine Due Diligence |
- |
2009 |
| Germany, portfolio, 6 wind farms |
Technical Due Diligence |
55 MW |
2010 |
| Germany, portfolio, 3 wind farms |
Technical Due Diligence |
40 MW (15 x V90-2,0 MW, 3 x MM92-2,0 MW) |
2010 |
| Romania, 1 wind farm |
Negotiation maintenance contract |
45 MW |
2010 |
| Romania, 1 wind farm | Commissioning assessment | 348 MW (139 x GE-2.5 MW) |
2010 |
| Romania, 1 wind farm |
Construction Supervision |
45 MW (15 x V90-3 MW) |
2010 |
| Poland, 1 wind farm |
Technical Due Diligence |
20 MW |
2010 |
| Poland, 1 wind farm | Technical Due Diligence | 50 MW | 2010 |
| France, 3 wind farms | Construction supervision | 35 MW (15 x E70-2,3 MW) | 2010 |
| Germany, 2 planned wind farms | Technical Due Diligence | 13,5 MW | 2011 |
| Germany, portfolio, 5 wind farms | Technical Due Diligence | 72,5 MW (18 x E66-1,8 MW, 20 x E70-2,0 MW) | 2011 |
| Germany, 1 wind farm | Short Technical Due Diligence | 17 MW (5 x REpower 3,4M104) | 2011 |
| Germany, portfolio, 3 wind farms | Short Technical Due Diligence | 50 MW (25 x V80-2,0 MW) | 2011 |
| Germany, 1 wind farm | Construction supervision | 12,5 MW (5 x N100-2,5 MW) | 2011 - 2012 |
| Romania, 1 wind farm | Commissioning inspection | 45 MW (15 x V90-3 MW) | 2011 |
| Kazakhstan, 1 wind farm | General consulting services | 45 MW | 2011 |
| Australia, 1 wind farm | End of warranty inspection | 70 MW (35 x E-70-2,0 MW) | 2011 |
| Romania, 1 wind farm | End of warranty inspection | 348 MW (139 x GE-2.5 MW) | 2012 |
| Poland, 1 wind farm | Foundation assessments | 48 MW (24 x V80) | 2012 |
| France, 1 wind farm | Technical Due Diligence | 16 MW (7 x E-70-2,3 MW) | 2012 |
| Italy, 1 wind farm | Turbine inspections | 18 MW (12 x S779 | 2012 |
| Spain, 1 wind farm | Technical Due Diligence | 16 MW (9 x V90-1,8 MW) | 2012 |
| Greece, 1 wind farm | Commissioning | 29 MW (34 x V52-850 KW) | 2012 |
| South Africa, 1 wind farm | Technical Evaluation of different turbine concepts | - | 2012 |
Offshore
| Project | Project | Remarks | Year |
|---|---|---|---|
| Offshore wind park |
Production Monitoring (TP’s) | 367 MW | 2011 |
|
Collision Analysis |
200 MW |
2011 | |
| Consulting Services |
288 MW |
2010–2011 |
|
| Factory Inspections, Collision Analysis, Consulting Services | 400 MW (offshore) |
2011 | |
| Owner’s Engineer, Project Support |
– |
2011 | |
| Inspection of offshore WTG |
1 x 2.3 MW turbine |
2011 | |
| WTG evaluation |
– |
2011 | |
| Sample gearbox inspections |
55 x 3 MW turbines |
2010 | |
| Factory inspections and quality assurance |
400 MW |
2010–2012 | |
| Collision Analysis |
288 MW | 2010–2011 |
|
| Negotiation preparation and assistance with turbine manufacturer, |
288 MW |
2010–2011 |
|
| Negotiation input for quality assurance and factory inspections |
288 MW |
2010 | |
| Construction supervision and commissioning assessment of 5.0 MW turbines, lifecycle prognosis |
400 MW |
2010–2012 |
|
| Quality Assurance for monopiles |
367,2 MW |
2010–2011 |
|
| Update of the Due Diligence study |
400 MW |
2009 | |
| Offshore test field |
Construction supervision and commissioning assessment of the first German offshore wind park |
60 MW |
2009–2010 |
| Offshore wind park |
Due Diligence |
288 MW |
– |
| Due Diligence of possible turbines for the project in the range of 3.6 – 5 MW |
– |
2009 | |
| Negotiation assistance with turbine manufacturer |
55 x 3 MW turbines |
2008–2009 |
|
| QA/QC management for all offshore foundation structures |
55 x 3 MW turbines |
2008–2009 |
|
| Due Diligence for the possible purchase of the project (executed), wind park to be built in 2010 |
400 MW |
2008 | |
| Offshore wind park |
Negotiation assisstance |
400 MW |
2008–2009 |
| Turbine Due Diligence |
Due Diligence of 3 potential offshore turbines |
– |
2008 |
| Offshore wind park |
Re-calculation of decommissioning costs |
90 MW |
2007 |
| Offshore test field |
Technical adviser, factory inspections, quality control |
60 MW |
2007–2009 |